Last Planner® System Saves Time

6th LPS 5 Steps

Construction companies that use the Last Planner® System have completed projects months in advance of scheduled completion date.

By planning in advance you avoid the typical all-out rush at the end of a project. By focusing on the overall goal of the project and not the speed of individual subcontractors, you can finish things faster.

This is best shown through real-life projects that finished ahead of schedule.

 

Project Scheduled Completion (Months) Actual Completion
Seattle Children's Hospital 18 14
Wisconsin Hospital 38 36
St. Louis Hospital 26 24
Toronto Tenant Finish 14 8
University Stadium East Stands 10 8

 

See: http://themilitaryengineer.com/tme_mag/07_08_2013/TME-JulyAug2013-Online-SM.pdf.

Suffolk Construction has demonstrated savings in both time and money in two of their recent projects:

  1. Los Angeles Unified School District (LAUSD) South Region Middle School #3. The school was completed 2 months ahead of schedule AND saved approximately $1.05 million.
  2. Massachusetts College of Art and Design (Mass Art). After implementing Lean principles, Suffolk was able to cut 2 months off of the original project timeline.
Last Planner® System: 5 Steps to Efficiency
Best Practices: Last Planner® System

About Author

Default Author Image
Touchplan

Related Posts
How Project Teams Can Adapt During COVID-19
How Project Teams Can Adapt During COVID-19
Recap: LCI Congress 2019
Recap: LCI Congress 2019
Touchplan at GLCI Karlsruhe
Touchplan at GLCI Karlsruhe

Comment

Subscribe To Blog

Subscribe to Email Updates